// PROJECT TIMELINE

Renovation Project
Timeline Calculator

List your tasks, how many days each takes and what must finish first. The timeline schedules everything in order and shows how long the whole project will take.

  • Task dependencies
  • Total project days
  • Up to 50 tasks

Project task schedule

Choose each task's prerequisite. Independent tasks run in parallel. Duration is in calendar days, not working days.

TaskDaysDepends on

Estimated project duration: 11 days

Scheduling assumes unlimited crew availability, no holidays, no weather delays and one prerequisite per task in this editor. Not a contractor commitment.

// HOW IT WORKS

How the schedule is built.

  1. Add tasksGive each task a name and a duration in calendar days.
  2. Link themPick the task that must finish first, such as rough-in before drywall.
  3. ScheduleEach task starts when its last dependency ends. Tasks with nothing in common can run at the same time.
  4. TotalThe project length is the end of the last task.

// WORKED EXAMPLE

A bathroom remodel.

Each task waits for the one before it.

  • Demolition: days 0–2
  • Plumbing & electrical rough-in: days 2–5
  • Drywall: days 5–9 · Prime & paint: days 9–11
  • Flooring: days 11–13 → 13 days total
Project schedule5 tasks · back to back024681012Demolitionday 0–22dRough-inday 2–53dDrywallday 5–94dPrime & paintday 9–112dFlooringday 11–132dDone · 13 days
Diagram uses the worked example's inputs · not to scale

// TIPS

A typical renovation order.

Demo and structure

Remove old finishes first, then fix framing or structure you uncover.

Rough-ins and inspection

Plumbing, electrical and HVAC go in before walls close. Inspections often happen here.

Close up and finish

Insulation, drywall, primer and paint, then flooring, trim and fixtures last.

Add buffer days

Allow for drying times, deliveries and inspection appointments. They rarely line up perfectly.

Questions

What does a circular dependency mean?

Two tasks are waiting for each other, so neither can start. Remove one of the links.

Can tasks overlap?

Yes. Tasks that don't depend on each other start at the same time.

Does it skip weekends?

No. Durations are calendar days, so include weekends and days off in each task's length.

Keep planning